A building ordered too late does not protect anything this year. Here are current lead times, and the last realistic date to order so it is standing before December.
Counting back from December 1, using today’s build times plus about 2 weeks for delivery scheduling.
Wood Sheds
~4 week build · ~6 weeks total
Order by
October 20
Order today and expect installation around October 24.
Browse Wood ShedsMetal Buildings
~12 week build · ~14 weeks total
Custom orders are past the line
August 25
A custom order placed today would land around December 19. In-stock buildings are the realistic route now.
Browse Metal BuildingsGreenhouses
~5 week build · ~7 weeks total
Order by
October 13
Order today and expect installation around October 31.
Browse GreenhousesThese dates are calculated from current build times, which move with demand and weather. Treat them as a planning guide, not a guarantee — and call us if you are close to the line, because we can often tell you same-day whether it is achievable.
Past the order-by date on something you need? It is not necessarily over. In-stock buildings bypass the build queue completely, and the lots hold buildings in the most common sizes. Check current inventory before assuming you have to wait until spring.
Lead time is not one queue. Knowing where it goes tells you which parts you can influence and which you cannot.
1. Order confirmation and specification
Size, colours, doors, windows, anchoring. Fastest when you know what you want — the 3D builder gets this sorted before you call.
2. Manufacturing
The bulk of the wait, and the part nobody can shortcut. It moves with demand, which is exactly why autumn is easier than spring.
3. Delivery scheduling
Routing a truck and crew to your site. Usually a week or two, longer if access is difficult or the weather closes in.
4. Installation
Most residential installs finish in a single day — provided the site is ready. If it is not, this is where the timeline breaks.
Buy from stock
Buildings already built at a lot skip manufacturing entirely, which is most of the wait. You give up some choice on colour and configuration; you gain weeks.
See what is in stockPrep your site now
Site prep runs in parallel with manufacturing, so doing it early costs you nothing and removes the most common cause of a delayed install. It also gets much harder once the ground freezes.
Tell us your deadline
If you have a hard date, say so when you order. We will tell you honestly whether it is achievable and what would have to change — rather than you finding out in November.
We will tell you straight whether it is achievable, and what your fastest route is. No pressure if the answer is spring.